DRAM is on 20-26 weeks lead time from Micron and Samsung rising to 26-30 weeks for DDR3 and DDR4.

NAND is on 20-26 weeks from Kioxia

General Discretes are on 20-36 weeks at ST, 20-32 weeks at Nexperia, and 26-40 weeks at Infineon.


Power Discretes are on 50-60 weeks at ON, 26-52 weeks at Diodes, 39-52 weeks at Wolfspeed and 52-70 weeks at Infineon.

PMICs are on 30-34 weeks at ADI, 30-45 weeks at infineon, 50-60 weeks at TI, 30-40 weeks at ST

Embedded Processors 

8-bit – 32-75 weeks at Microchip; 45-65 at ST, 26-52 at Infineon; 35-75 at TI

16-bit. – 52-65 weeks at NXP; 32-75 weeks at Microchip; 45-65 at ST; 18-20 weeks at Intel;14-26 at AMD 

32-bit – 55-99 weeks at NXP; 52-65 at ST; 20-52 at Infineon; 40-50 at Si Labs; 

Programmables: 45 weeks for FPGA and CPLD from Intel